Winchester Ave. Improvements and Streetscape project Phase B to begin Nov. 20

Information For

Winchester Ave. Improvements and Streetscape Project update! ��

Contractors are finishing up pouring the medians this week. Beginning the week of Monday, Nov. 20, Phase B of the project will begin. Here’s what you need to know:

⚠️ Starting Nov. 20, contractors will begin milling the outside lanes (where you are driving now) up to the curb.
⚠️ Traffic flow will be shifted to the inside lanes (next to the median, where the barrels are) in each direction starting Wednesday, Nov. 22.
⚠️ Parking will only be impacted on the specific block they are working on. All other parking will be available. Once they are finished with the block they're working on, parking will reopen.
⚠️ Starting Monday, Nov. 27 contractors will begin work on the sidewalks starting at the river side of 13th St. and Winchester Ave.
⚠️ There will be continuous access to businesses during sidewalk construction.